WE Report

Lessons Learned

Lesson Learned





By: Drilling Engineer

Report No.

2273

Discipline/Origin

Logistics
Own Experience

Well

Fat Canyon
6306/3-1 S

Date created

2021/11/05
1492 days ago

Project Phase

Operational
Project Phase

LL Type/Classification

Mud
Negative

Borgland Dolphin


What happened in Production section:
During operation drilling did go slower than expected and way too often the boats has to go to the base only to pick up mud chemicals. For example today, 05.11.2021, there is suddenly very little mud chemicals left, after we asked the mud engineer yesterday if he was good, and he said yes. Now, chemicals are express shipped to base and the boat has to go in just to pick that up.

What Was Planned

To have sufficient amount of mud chemicals.

What Was Learned

The mud chemicals has to be planned better so one doesn’t need to send the boat back and forth just because of the chemicals. One shall try to ship more together and make a plan of mud and chemicals that can at least hold for a week.

What Actions Are Required

Send out bigger batches of mud chemicals.